Overview

For a data centre, the substation sets three things that cannot easily be changed later: how much power the campus can ever draw, how reliably it arrives, and the date the first megawatt is available. It is also the longest lead item on most programmes, bound up with the transmission utility’s own studies, approvals and outages. We treat it as the first building on the campus: planned for the final load, sized with redundancy that matches the data halls it serves, and engineered, procured and energised by one team.

CS-604.1GIS or AISSection A

Choosing the right insulation for the site.

An air-insulated substation places its equipment in the open air, spaced for insulation. A gas-insulated substation encloses busbars, breakers and disconnectors in sealed, gas-filled compartments. The choice is made from the site, not from habit, and hybrid arrangements combine the two where it pays.

CriterionAir-insulated (AIS)Gas-insulated (GIS)
FootprintLarge outdoor yard with wide clearancesA fraction of the area, often inside a building
EnvironmentExposed to dust, pollution, coastal salt and heavy monsoonEnclosed and sealed, largely unaffected by climate
Reliability and maintenanceRegular cleaning and inspection of exposed partsLong maintenance intervals, gas monitored continuously
SafetyLive parts at height, controlled by clearances and fencingEarthed metal enclosures, no exposed live parts
Build and expansionSimple to extend where land is reservedFactory-tested bays, quick to erect, extended bay by bay
Insulating gasNot applicableSF6 or lower-impact alternatives, with leak monitoring and gas handling
Where we use itLarge rural plots with clean air and room to growUrban, constrained, coastal or polluted sites, and campuses where land is better used for data halls
CS-604.2ScopeSection B

Nine disciplines in one substation.

A substation brings together power systems, primary and secondary engineering, civil and structural design and a long list of statutory approvals. We cover each of them, and coordinate them with the campus they feed.

S1Grid

Connection and load application

Load forecast for the final campus, application to the transmission utility, connectivity studies and the connection agreement.

S2Studies

Power system studies

Load flow, short circuit, protection coordination, insulation coordination, harmonics, transient and stability studies.

S3Configuration

Single line and layout

Double busbar, one-and-a-half breaker or ring arrangements, chosen for the reliability the data halls require.

S4Primary

Primary equipment

GIS or AIS bays, power transformers, reactors and medium-voltage switchgear from HyperNext approved brands.

S5Secondary

Protection, control and SCADA

Numerical protection, IEC 61850 substation automation, and links to the utility’s load dispatch centre and the campus BMS.

S6Earthing

Earthing and lightning protection

Soil resistivity survey, earth mat design for safe step and touch potentials, and shielding of the yard and building.

S7Civil

Buildings and foundations

GIS halls with overhead cranes, cable cellars, transformer bays with fire walls and oil containment, roads and drainage.

S8Lines

Line and cable entry

Overhead line or underground cable entry, line-in line-out arrangements and right of way.

S9Auxiliary

Auxiliary systems

Station batteries and DC systems, auxiliary transformers, transformer fire protection and gas handling equipment.

CS-604.3Designed for data centresSection C

What a data centre asks of its substation.

A data centre load is large, constant and intolerant of interruption, and it grows in steps over many years. The substation is designed around those facts.

  1. Two sourcesSupply from two independent grid circuits or substations wherever the network allows.
  2. Transformer redundancyCapacity to carry the full load with any one transformer out of service.
  3. Built for the final loadLand, bays, line entries and corridors fixed for the final campus, with transformers added phase by phase.
  4. Power qualityHarmonics from rectifiers, UPS and 800 VDC conversion studied and filtered at the right level.
  5. Campus distributionMedium-voltage rings to every building, with switching that isolates a fault without dropping a hall.
  6. Renewable injectionBays for captive solar, wind and battery storage, so green power enters through the same intake. See Green power arrangement.
  7. First power earlyLong-lead equipment ordered on the concept design, so energisation does not set the date of the first hall.
  8. Clear ownershipUtility-owned, consumer-owned or shared arrangements settled at the start, with the handover boundary drawn.
CS-604.4MethodSection D

Eight stages, from load forecast to energisation.

The utility’s process and our own run in parallel, so that studies, approvals and procurement do not wait on one another.

SS-01

Load and application

Final and phased load forecast, voltage level, and the application to the transmission utility.

OutputLoad application
SS-02

Connectivity and studies

Connectivity studies with the utility, and our own load flow, short circuit and reliability studies.

OutputStudy reports
SS-03

Concept

GIS or AIS, bus configuration, single line diagram, layout and the route of the line or cable entry.

OutputConcept design and SLD
SS-04

Approvals

Transmission utility and electrical inspectorate approvals, CEA safety regulations, land, right of way and any forest or environmental clearances.

OutputApprovals in place
SS-05

Detailed design

Primary and secondary engineering, earthing, civil and structural design, issued as a complete, coordinated set.

OutputIssued drawings and BOQs
SS-06

Procurement

Tenders against the specification, with type test evidence and factory acceptance tests witnessed before dispatch.

OutputOrders and FAT records
SS-07

Construction

Civil works, GIS erection or yard construction, transformer installation, cabling and line or cable entry.

OutputProgress record
SS-08

Testing and energisation

Pre-commissioning tests, protection and SCADA testing, inspectorate clearance and energisation with the utility.

OutputEnergisation certificate
Start a project

Planning a substation?

Send the site, the final load and the voltage on offer. We will set out the connection route, the configuration and the programme to first power.