Overview

Before a plot is purchased or a single drawing is started, we establish what the ground, the grid and the surrounding infrastructure will allow. The ground study records the physical facts of the site, from bearing capacity and flood level to soil resistivity and fibre routes, and turns them into a clear statement of what can be built there, at what scale and at what risk.

CS-101.1Site selectionSection A

Choosing between sites on evidence, not impression.

Most clients arrive with more than one candidate site, or with a single plot and a question about whether it is suitable. We compare candidates against the same weighted criteria and present the result as a scored matrix, so that the reasoning behind a recommendation can be examined by a board, a lender or a tenant.

The criteria are set by the kind of facility intended. A primary hyperscale campus weighs grid capacity and expansion land most heavily; a disaster recovery site weighs its separation from the primary, its seismic and flood exposure and the diversity of its fibre routes; an enterprise facility weighs proximity to the people who will operate and use it.

A1Power

Grid strength and distance

Available capacity at the nearest substations, voltage level, line length, the state transmission plan and the realistic date for connection.

A2Fibre

Routes and diversity

Long-haul and metro fibre within reach, the number of physically separate entry routes, and distances to carrier hotels and cable landing stations.

A3Hazard

Natural risk

Seismic zone, basic wind speed, cyclone exposure, flood history and highest flood level, lightning density and proximity to industrial hazards.

A4Land

Title, zoning and shape

Clear title, permitted use, conversion requirements, plot geometry, setbacks, height limits and the land needed for later phases.

A5Access

Logistics and people

Road widths and turning radii for transformer and rack deliveries, crane access, distance to airports and ports, and travel time for operating staff.

A6Policy

State framework

Data centre policy incentives, open access and banking rules for renewable power, and the record of approvals in the district.

CS-101.2Ground studySection B

The physical record of the site.

Once a site is preferred, we commission and supervise the surveys that the design will depend on. Each survey is specified by the discipline that will use its results: the structural engineer specifies the boreholes, the electrical engineer specifies the soil resistivity readings, and the civil engineer specifies the levels and drainage survey. Results are reviewed against Indian standards before they are accepted, and every figure is carried directly into the feasibility model and the design basis.

A data centre is heavier than most commercial buildings. Rack-scale systems weigh up to 3.5 tonnes each, and we design data hall floors for 2,800 kg/m², so the geotechnical investigation is planned for those loads from the beginning rather than discovered at the structural stage.

RefSurveyWhat it establishesUsed by
GS-01Topographic surveyLevels at close grid spacing, existing features, trees, services and boundaries, tied to a fixed benchmarkMaster plan, civil, drainage
GS-02Geotechnical investigationBoreholes with standard penetration tests, plate load tests, groundwater level and laboratory testing for foundation designStructure, foundations
GS-03Soil resistivityResistivity at several depths and directions for earthing and lightning protection designElectrical, earthing
GS-04Hydrology and floodCatchment, natural drainage paths, highest flood level and the plinth level that clears itCivil, master plan
GS-05Seismic and windZone and design parameters to IS 1893 and IS 875 for the structure and for rooftop plantStructure, mechanical
GS-06Utilities and fibreLocation and capacity of power lines, water, sewer and fibre in and around the sitePower, network, plumbing
GS-07Climate recordFifty years of site weather for cooling plant sizing and annual efficiency modelling in CFD StudioMechanical, feasibility
GS-08Environmental baselineAir, noise, groundwater and ecology baseline where an environmental clearance will be requiredApprovals
CS-101.3Power firstSection C
A 220 kV substation beside a data centre site
Fig. 01  220 kV substationNTS
Grid connection

The hardest infrastructure is placed first.

A site study begins with the grid, because the connection is usually the longest-lead item on a data centre programme. We establish the capacity available at the nearest substations, the voltage at which the site can connect, the line route and the realistic date on which power can be drawn, and we size the request for the final campus rather than the first phase, so that later buildings are never left waiting for power.

If the ground and the grid cannot support the intended facility, the study says so early, while the cost of changing course is still small.

CS-101.4DeliverablesIssue schedule

What the study hands over.

The site and ground study closes with a written report and a set of drawings that become the base for the feasibility model and the master plan. All drawings are issued as DXF and PDF on the surveyed coordinate system.

  1. Site comparison reportScored matrix of candidate sites with the weighting explained.
  2. Survey drawingsTopographic, utilities and boundary survey in DXF and PDF.
  3. Geotechnical reportBorehole logs, test results and foundation recommendations.
  4. Hydrology noteFlood level, drainage strategy and recommended plinth level.
  5. Earthing basisSoil resistivity results and the earthing design approach.
  6. Constraints planSetbacks, easements, hazards and buildable area on one sheet.
Start a project

Start with the ground.

Send the location and the facility you have in mind. We will tell you which surveys the site needs and what the grid is likely to allow.