A data centre park places several buildings on one site behind a common intake, a common security line and a common set of utility corridors. Its value depends on decisions that are taken once, at the master plan, and then lived with for decades: where the substation stands, how the corridors run, which routes the fibre takes and how each later building connects without disturbing those already in service.
The elements a park master plan must settle.
The master plan is drawn to the same standard as a building set: fully dimensioned, on the surveyed coordinate system, with levels, sections through the corridors and a phasing sequence that shows what is built, energised and occupied at each stage. It is the document every later building is designed against, and it is issued final, so that the first building does not compromise the sixth.
Building pads and phasing
Plot sizes for each building type, setbacks, height envelopes and the order in which plots are developed, so that construction never crosses an operating building.
Shared high-voltage intake
One substation sized for the final park, with a 33 kV ring or radial network to each building and space reserved for every future feeder.
Utility corridors
Cable trenches, duct banks, water and drainage mains in dedicated corridors, sized for the whole park and crossing roads at planned points only.
Diverse routes and meet-me rooms
At least two physically separate fibre entries to the park, a campus ring between buildings and carrier-neutral meet-me rooms in more than one building.
Layered perimeter
A park boundary, vehicle screening at the gate, a building line and a hall line, each with its own access control and its own record.
Roads and logistics
Road widths, turning circles and pavement design for transformer deliveries and 3.5-tonne racks, with separate routes for staff, visitors and freight.
Shared facilities
Operations and security centre, warehouse and staging, loading, fuel storage, water treatment and the amenities for people who work on site.
Levels and drainage
Finished levels above the highest flood level, storm water routed to retention, and landscape that keeps heat and dust away from the plant.
Expansion land
Land and corridor capacity held for buildings not yet planned, and a written rule for how each one connects to the shared systems.
Designed once, repeated across the park.
On a park, the elements that are common to every building are identified first and designed once as a standard set: plant rooms, risers, CDU rooms, electrical rooms, prefabricated services skids and the connections to the corridors. Each building then places those standard blocks by tag and location rather than redrawing them, which shortens design, simplifies procurement and allows the fabricator to produce identical skids in quantity.
On a six-building park, all six drawing sets go to the fabricator together with a schedule of identical skids, so that manufacture is planned for the whole park rather than one building at a time.
One park, several ways to lease.
A park can serve several kinds of tenant at once. The master plan and the feasibility model are prepared together so that each plot is matched to the commercial model it will carry, and the shared infrastructure is charged fairly between them.
| Model | What the tenant receives | What the park provides |
|---|---|---|
| Powered land | A serviced plot with power, fibre and water at the boundary | Intake, corridors, security and common facilities |
| Powered shell | A completed building envelope with power to the building | As above, plus the shell, core and main plant spaces |
| Build-to-suit | A complete building to the tenant’s own reference design | Design, procurement, construction and fit-out to that design |
| Wholesale halls | Whole data halls in a multi-tenant building | Building, plant and operations, with the hall fitted to the tenant |
| Colocation | Racks, cages and suites | Everything up to the rack, operated by the park |
Many states offer specific incentives for data centre parks, covering land, power tariff, stamp duty and open access. We prepare the park-level approvals once, so that individual buildings and tenants do not each repeat them. See Approvals.
Thinking from the practice.
Short perspectives from our engineers on the decisions that shape a data centre.

Why 800 VDC takes the UPS room out of the building
Single conversion from 33 kV to the rack removes rooms, losses and a fire risk, and lets density change without new panels.

Renewable power should be measured by the hour
Annual renewable claims hide the night. Hourly matching shows what a data centre actually runs on.

Planning a site for 3.5-tonne racks
Rack-scale AI changes the ground study, the structure and every route from the loading dock to the hall.
Plan the park once.