HyperNext Consulting Service · A proud member of HyperNext Group
Overview

The fastest site is the one where the services arrive finished. Design for manufacture and assembly moves pipework, pumps, cooling, cable containment and power distribution out of the building and into the factory, where they are built to tolerance, tested under controlled conditions and shipped while the structure is still rising. It only works if the design is complete and coordinated first. That is where we begin.

CS-205.1ScopeSection A

Mechanical, electrical and power, made off site.

We prefabricate wherever a system repeats, wherever site labour is scarce or unsafe, and wherever factory testing will catch what site testing would find too late.

P1Mechanical

Pump and plant skids

Chilled water, condenser water, fire pump and booster sets on common frames, piped, valved and wired.

P2Cooling

Liquid cooling skids

Coolant distribution and secondary loops for direct-to-chip cooling, with drip trays and leak detection under every liquid pipe.

P3Multi-service

Pipe-rack and corridor modules

Pipes, cable trays, busduct and lighting combined in one frame, lifted into corridors and plant spaces in a single piece.

P4Electrical

Electrical skids

Low-voltage boards, distribution and rack power panels assembled with containment and tested as one unit.

P5Power

Power modules and e-houses

Medium-voltage switchgear, transformers and protection in factory-built enclosures, ready to connect.

P6Plumbing

Plant rooms and risers

Water treatment, plumbing and drainage assemblies, and riser modules stacked floor on floor.

CS-205.2Design rulesSection B

The rules that make prefabrication pay.

Prefabrication saves time only when the design is written for the factory. These rules apply to every skid and module we design.

  1. Common blocks firstBlocks shared by every building on a campus are designed once, as a standard set, before any building-specific work.
  2. Types and quantitiesSkids with identical parameters are grouped into types, with the quantity and the skid numbers of each, so the factory can build in series.
  3. Sized for the routeEvery module is dimensioned to pass through the building’s openings and be set in place with scissor lifts.
  4. Leaks containedDrip trays with leak detection under all liquid pipework, on every skid and in every design.
  5. Traceable partsOne barcode per skid, and a readable part code on every item giving material, location, skid number and design number.
  6. Final at first issueCoordination, codes and factory requirements resolved before manufacturing drawings are issued, so nothing is revised in fabrication.
  7. Connections auditedEvery pipe, cable and signal checked end to end, from source to load, across skid boundaries.
  8. Drawings for the makerFully dimensioned CAD manufacturing drawings, with schedules and bills of quantities kept in separate registers.
CS-205.3MethodSection C

Seven stages, model to hook-up.

The sequence runs in parallel with civil works, so the services are ready when the building is.

PF-01

Coordinated design

Architecture first, then every service coordinated in one model, with cross-sections through the whole building.

OutputCoordinated model
PF-02

Module split

The services divided into skids and modules along the lines that suit the factory, transport and the route into the building.

OutputModule plan
PF-03

Type schedule

Identical skids grouped into types, quantities fixed, highest-quantity types released first.

OutputType and quantity schedule
PF-04

Manufacturing drawings

Dimensioned drawings, part codes and bills of quantities for each type, issued floor by floor.

OutputManufacturing set
PF-05

Factory build

Fabrication monitored against the drawings, with inspection at agreed hold points.

OutputInspection records
PF-06

Factory acceptance

Pressure, flushing, electrical and functional tests witnessed in the factory before dispatch.

OutputFAT certificates
PF-07

Delivery and hook-up

Delivered in installation order, set by tag and location ID, connected, and tested again on site.

OutputSite acceptance record
CS-205.4OutcomesSection D

What the owner gains.

The benefits of prefabrication are measured on the programme, on site safety and in the condition of the services at handover.

OutcomeHow prefabrication delivers it
Shorter programmeServices built in the factory while the structure is built on site
Consistent qualityWelding, assembly and testing under factory conditions, to one standard
Safer sitesLess work at height and fewer trades working in the same space
Less wasteMaterials cut to schedule in the factory, with offcuts recovered
RepeatabilityThe same skid types reused across buildings and campuses
Start a project

Planning a prefabricated build?

Send the building type, the services in scope and the programme. We will set out what can be made off site and how much time it saves.

ReplyWithin one working day, from an engineer
OfficesMumbai · Bangalore · Ahmedabad · Toronto
PracticeHyperNext Consulting Service, a proud member of HyperNext Group