Building services are prefabricated into skids in a factory while the structure rises, delivered numbered and lifted into place. The site team then manages construction, safety and the infrastructure fit-out of each hall, through containment, power, cooling and fibre to the rack position, and tests and commissions every system before the building is handed over ready for load.
The factory builds; the site assembles.
The elements common to every building on a campus are identified and designed first as one standard set, so the fabricator can produce identical skids in quantity. Skids with the same parameters are grouped into types, each drawing shows the quantity and the skid numbers it covers, and the type with the highest quantity is manufactured first.
Each skid carries one barcode, and every item on it carries a readable part code recording its material, location, skid and design number, so that anyone on site can trace a fault or have a part remade. Skids are sized to pass through the building’s openings and be raised into position on scissor lifts, and every connection is audited end to end before the drawings are released to the factory.
| Ref | Element | Method |
|---|---|---|
| PF-01 | Glycol cooling pipework | Prefabricated, with drip trays and leak detection under every run |
| PF-02 | Air and smoke ducts | Prefabricated |
| PF-03 | Cable trays, ladders and busduct runs | Prefabricated, with busduct kept inside the building |
| PF-04 | Fibre raceway | Prefabricated |
| PF-05 | Shared multi-service racks | Prefabricated, carrying several services in one frame |
| PF-06 | Fire protection and plumbing | Installed on site by the specialist trades |
| PF-07 | Brazed refrigerant pipework | Installed on site |

From an empty hall to a hall ready for load.
Infrastructure fit-out is the stage at which a finished shell becomes usable capacity. We set out rack positions from the issued drawings, install containment, bring 800 VDC or AC power to each position, extend the secondary cooling loop to the racks that need liquid, run fibre and structured cabling, connect every sensor to the BMS, and test each hall before a tenant moves in.
- Set-outRack rows, containment and service zones marked from the coordinated drawings.
- Power to positionRack power panels and whips to each rack, with no tap-off boxes.
- Liquid to rackSecondary loop and manifolds from the CDU room, pressure tested and flushed.
- Fibre and cablingOverhead raceway, patching and labelling to the network design.
- MonitoringEvery point connected to the BMS and tested before handover.
Managed, safe, tested and handed over.
One site team carries the work from mobilisation to handover. A vendor reaches site only in a fixed order: drawings reviewed and approved, the purchase order placed, and only then a gate pass issued.
Construction management
Programme, interfaces between trades, daily progress and quality records, and a single point of responsibility on site.
Safety and access
Gate passes issued after drawing approval and order, badges collected from the main security office, no phones in data halls and no smoking anywhere on campus.
Testing and commissioning
Factory acceptance, site acceptance and integrated systems tests, witnessed and recorded, with every result on file before load is applied.
Handover
As-built drawings in DXF and PDF, operation and maintenance records, the approvals register and an operations team trained on the building.
Thinking from the practice.
Short perspectives from our engineers on the decisions that shape a data centre.

Why 800 VDC takes the UPS room out of the building
Single conversion from 33 kV to the rack removes rooms, losses and a fire risk, and lets density change without new panels.

Renewable power should be measured by the hour
Annual renewable claims hide the night. Hourly matching shows what a data centre actually runs on.

Planning a site for 3.5-tonne racks
Rack-scale AI changes the ground study, the structure and every route from the loading dock to the hall.
Ready to build?
Send the drawings or the brief. We will return a programme, a prefabrication plan and a fit-out sequence.