A data centre needs consents from many authorities, and the order in which they are obtained matters as much as the applications themselves. We map every approval the site will need at the outset, with its authority, its dependencies and its lead time, and run the applications alongside the design, filed from the same drawing set the contractor will build, so that approvals never hold up the programme.
Eight families of consent, each with one owner.
Each approval is assigned to a named owner on our side, who prepares the application from the coordinated design, answers the authority’s queries with the relevant discipline engineer, and reports its status every week. Because the filings and the construction drawings come from the same set, the building that is inspected is the building that was approved.
| Ref | Approval | Scope | Authority |
|---|---|---|---|
| AP-01 | Power | Load allocation, connectivity, substation and, where used, open access approvals | State transmission and distribution companies, nodal agency |
| AP-02 | Land | Conversion of use, zoning and layout approval | Revenue and planning authorities |
| AP-03 | Building | Building plan approval to the National Building Code and local development rules | Municipal or development authority |
| AP-04 | Environment | Environmental clearance where thresholds apply; consent to establish and consent to operate | State pollution control board and environment authority |
| AP-05 | Fire | Fire NOC to NBC Part 4, from design approval through to occupation | State fire services |
| AP-06 | Electrical | Inspection and approval to the CEA safety regulations before energisation | Electrical inspectorate |
| AP-07 | Generators | Emission and noise compliance for diesel generator sets and fuel storage | Pollution control board, explosives authority where applicable |
| AP-08 | Incentives | State data centre and data centre park policy benefits: land, tariff, stamp duty and capital subsidy where offered | State IT and industries departments |

Applications that authorities can approve the first time.
Most approval delays come from applications that do not match the design, or from questions that reach the authority before the design team has answered them. We prevent both by filing from the coordinated drawing set and by placing the discipline engineer, not a liaison agent, in front of the authority when technical questions arise.
- State engagementInvestment facilitation, data centre policy incentives and memoranda with state governments.
- Utility engagementLoad applications, connection studies and substation coordination with transmission and distribution companies.
- Statutory consentsBuilding, fire, environment and electrical approvals filed from the issued design.
Four stages, from map to register.
The approvals programme is part of the master programme, and its critical items, usually the power connection and the environmental consent, are started during the feasibility study rather than after design.
Map
Every approval the site needs, with its authority, dependencies and lead time, set out on one programme.
OutputApprovals route mapPrepare
Applications drawn from the coordinated design set, so that the drawings filed are the drawings built.
OutputApplication packsFile and follow
One owner for each approval, queries answered with the discipline engineer, and status reported to the client every week.
OutputWeekly approvals reportClose
Certificates, consents and conditions filed with the handover record, with renewal dates tracked through operation.
OutputApprovals registerThinking from the practice.
Short perspectives from our engineers on the decisions that shape a data centre.

Why 800 VDC takes the UPS room out of the building
Single conversion from 33 kV to the rack removes rooms, losses and a fire risk, and lets density change without new panels.

Renewable power should be measured by the hour
Annual renewable claims hide the night. Hourly matching shows what a data centre actually runs on.

Planning a site for 3.5-tonne racks
Rack-scale AI changes the ground study, the structure and every route from the loading dock to the hall.
Clear the path.
Tell us the state and the site. We will map every approval it needs and the order in which to obtain them.