Every building on a campus inherits the decisions of its master plan. Where the substation stands, how power, water and fibre reach each building, how a 3.5-tonne rack travels from the gate to the hall, and how the fourth building is built beside three that are live: none of these can be corrected cheaply once the first building is in service. We plan the campus for its final capacity, then set out the phases so that each one is complete in itself and none disturbs the last.

CS-104.1What the plan fixesSection A

Nine systems, laid out for the final campus.

A master plan for a single-owner campus works from one brief and one operator. For plots shared by several tenants behind one intake, see Data centre parks.

M1Capacity

Capacity and phasing

Final IT load, number and size of buildings, and the sequence in which they are built and energised.

M2Power

Substation and corridors

The substation location, medium-voltage corridors to every building, generator and fuel yards, and renewable connections.

M3Cooling

Cooling and water

Plant locations, heat rejection, water sources, storage and treatment, with zero liquid discharge where required.

M4Network

Fibre and meet-me rooms

Two diverse fibre entries, campus ducts to every building and meet-me rooms placed for carriers and tenants.

M5Security

Security and access

Layered perimeter, gatehouses and separate routes for staff, visitors, deliveries and fuel.

M6Logistics

Logistics and construction

Delivery routes for heavy racks and plant, laydown areas, and construction access that never crosses a live building.

M7Landscape

Landscape and environment

Green cover, rainwater harvesting, storm drainage, noise control at the boundary and screening of plant.

M8People

Offices and amenity

Operations and security centres, offices, customer suites and amenity, placed away from plant and delivery routes.

M9Regulation

Development controls

Floor area ratio, set-backs, height limits, fire tender access and airport height clearances.

CS-104.2PrinciplesSection B

The rules every phase follows.

These principles are written into the master plan and handed to every designer who works on the campus after us.

  1. Build beside liveEach new building is connected without an outage or a crane over an operating hall.
  2. Corridors reservedRoutes for power, water and fibre are reserved for the final campus from the first phase.
  3. One standardCommon blocks are designed once and repeated, so every building is built and operated the same way.
  4. Short power pathsBuildings are arranged so that high-voltage and medium-voltage runs are as short and direct as possible.
  5. Clean and service sidesFuel, waste and heavy deliveries are kept apart from staff and visitor routes.
  6. Fire access all roundFire tenders can reach every face of every building.
  7. Headroom for changeSpace, structure and power reserved for higher densities and liquid cooling.
  8. Room to breathePlant spaced so that heat rejection from one building does not recirculate into another, checked by CFD.
CS-104.3MethodSection C

Six stages, from brief to approved layout.

The master plan follows the site and ground study and feeds the feasibility study model, so that capacity, phasing and cost are tested together.

MP-01

Brief and capacity

Final load, density, reliability, tenant types and the target date for first capacity.

OutputMaster plan brief
MP-02

Site analysis

Ground, flood, access, utilities, grid and fibre, and the development controls that apply.

OutputSite constraints plan
MP-03

Options

Alternative layouts tested for capacity, phasing, power path lengths, logistics and cost.

OutputOption study
MP-04

Preferred master plan

The chosen layout developed with building envelopes, plant yards, roads and landscape.

OutputMaster plan drawings
MP-05

Infrastructure plan

Substation, power, water, drainage, fibre and roads sized for the final campus and drawn in phases.

OutputInfrastructure plan
MP-06

Phasing and approvals

Phase sequence, layout approval and environmental clearance, with design guidelines for every later building.

OutputApproved layout and guidelines
Start a project

Planning a data centre campus?

Send the site, the final capacity you have in mind and the date you need first power. We will return a first layout and the phasing that fits it.

ReplyWithin one working day, from an engineer