Every building on a campus inherits the decisions of its master plan. Where the substation stands, how power, water and fibre reach each building, how a 3.5-tonne rack travels from the gate to the hall, and how the fourth building is built beside three that are live: none of these can be corrected cheaply once the first building is in service. We plan the campus for its final capacity, then set out the phases so that each one is complete in itself and none disturbs the last.
Nine systems, laid out for the final campus.
A master plan for a single-owner campus works from one brief and one operator. For plots shared by several tenants behind one intake, see Data centre parks.
Capacity and phasing
Final IT load, number and size of buildings, and the sequence in which they are built and energised.
Substation and corridors
The substation location, medium-voltage corridors to every building, generator and fuel yards, and renewable connections.
Cooling and water
Plant locations, heat rejection, water sources, storage and treatment, with zero liquid discharge where required.
Fibre and meet-me rooms
Two diverse fibre entries, campus ducts to every building and meet-me rooms placed for carriers and tenants.
Security and access
Layered perimeter, gatehouses and separate routes for staff, visitors, deliveries and fuel.
Logistics and construction
Delivery routes for heavy racks and plant, laydown areas, and construction access that never crosses a live building.
Landscape and environment
Green cover, rainwater harvesting, storm drainage, noise control at the boundary and screening of plant.
Offices and amenity
Operations and security centres, offices, customer suites and amenity, placed away from plant and delivery routes.
Development controls
Floor area ratio, set-backs, height limits, fire tender access and airport height clearances.
The rules every phase follows.
These principles are written into the master plan and handed to every designer who works on the campus after us.
- Build beside liveEach new building is connected without an outage or a crane over an operating hall.
- Corridors reservedRoutes for power, water and fibre are reserved for the final campus from the first phase.
- One standardCommon blocks are designed once and repeated, so every building is built and operated the same way.
- Short power pathsBuildings are arranged so that high-voltage and medium-voltage runs are as short and direct as possible.
- Clean and service sidesFuel, waste and heavy deliveries are kept apart from staff and visitor routes.
- Fire access all roundFire tenders can reach every face of every building.
- Headroom for changeSpace, structure and power reserved for higher densities and liquid cooling.
- Room to breathePlant spaced so that heat rejection from one building does not recirculate into another, checked by CFD.
Six stages, from brief to approved layout.
The master plan follows the site and ground study and feeds the feasibility study model, so that capacity, phasing and cost are tested together.
Brief and capacity
Final load, density, reliability, tenant types and the target date for first capacity.
OutputMaster plan briefSite analysis
Ground, flood, access, utilities, grid and fibre, and the development controls that apply.
OutputSite constraints planOptions
Alternative layouts tested for capacity, phasing, power path lengths, logistics and cost.
OutputOption studyPreferred master plan
The chosen layout developed with building envelopes, plant yards, roads and landscape.
OutputMaster plan drawingsInfrastructure plan
Substation, power, water, drainage, fibre and roads sized for the final campus and drawn in phases.
OutputInfrastructure planPhasing and approvals
Phase sequence, layout approval and environmental clearance, with design guidelines for every later building.
OutputApproved layout and guidelinesThinking from the practice.
Short perspectives from our engineers on the decisions that shape a building.

Why 800 VDC takes the UPS room out of the building
Single conversion from 33 kV to the rack removes rooms, losses and a fire risk, and lets density change without new panels.

Renewable power should be measured by the hour
Annual renewable claims hide the night. Hourly matching shows what a data centre actually runs on.

Planning a site for 3.5-tonne racks
Rack-scale AI changes the ground study, the structure and every route from the loading dock to the hall.
Planning a data centre campus?
Send the site, the final capacity you have in mind and the date you need first power. We will return a first layout and the phasing that fits it.