HyperNext Consulting Service · A proud member of HyperNext Group
Overview

We complete the architectural set before any services package begins, because electrical, mechanical, fire and plumbing systems cannot be designed responsibly into a building whose walls, levels and columns are still moving. Each services package is then drawn on that fixed base by the same team, coordinated floor by floor, and issued final, so that the set which leaves the office is the set the contractor builds.

CS-202.1PackagesSection A

Six disciplines, drawn as one set.

Every package is prepared on the same architectural base and coordinated with every other before issue. When a sheet in one package changes, the related sheets in the others change with it: support and mounting details, coordinated sections, containment routes and plumbing, so that no package is ever issued out of step with the rest.

ARArchitecture

The building

Site plan, a plan of every floor, elevations, sections, cores and circulation, room data and the structural loading brief for 2,800 kg/m² data hall floors.

ELElectrical

Power and earthing

High and medium voltage intake, 800 VDC or AC distribution to the rack, emergency generation, lighting and small power, with earthing on its own sheets.

MEMechanical

Cooling and air

Glycol loops, dry coolers, CDU rooms, air and smoke management, and comfort cooling for the spaces people occupy.

FPFire protection

Detection and suppression

Detection, two gas suppression rooms on opposite sides of each Tier IV hall, and pre-action sprinklers in the halls.

PLPlumbing

Water and drainage

Domestic supply, drainage, treatment and reuse through the sewage treatment plant, with no water drawn for cooling.

LVLow voltage

Systems and security

Fibre raceway, structured cabling, access control, CCTV and the field devices of the building management system.

CS-202.2Drawing standardGeneral notes

Twelve rules applied to every sheet.

These rules govern every drawing set the practice issues. They follow AECOM and Jacobs drafting practice and Indian standards at the highest class each offers. Their purpose is a set that can be priced accurately and built without a site office full of queries.

RuleRequirement
DS-01 SequenceArchitecture is completed first. Services are designed on a finished building and never ahead of it.
DS-02 PlansA plan sheet for every floor, each showing the whole floor. No typical-floor sheets and no split plans unless requested.
DS-03 DimensionsFull dimensions on every plan to engineering drawing standards, and detailed levels and dimensions on every section.
DS-04 SectionsCoordinated sections through the whole building, floor by floor, showing cable trays, ducts and pipes together.
DS-05 CalloutsNumbered callouts in place of text labels, keyed to a schedule in Excel, so that sheets read clean and nothing overlaps.
DS-06 SchedulesNo tables or schedules on drawing sheets. Text, schedules and specifications are issued in Excel.
DS-07 TaggingEvery electrical item and connection is tagged to the bill of quantities: what connects to what, at which level, on which system.
DS-08 EarthingEarthing is drawn on separate sheets and never mixed with power connections.
DS-09 LiquidDrip trays with leak detection under every liquid pipe, including those inside prefabricated skids.
DS-10 Layout checksNo column in the middle of a room or at a door, and circulation checked for staff, service personnel and escorted visitors.
DS-11 FilesOne DXF containing every sheet of a package, with the matching PDF set, in open formats.
DS-12 IssueFinal at first issue. Coordination, codes and prefabrication needs are resolved before anything leaves the office.
CS-202.3DetailsSection B
Stainless steel valve and sensor assembly on a glycol cooling line
Fig. 01  Inline fluid quality valve on a glycol lineNTS
Liquid cooling

Leaks are designed out before they can happen.

Direct-to-chip cooling brings glycol within reach of the most valuable equipment in the building. Every liquid pipe in our designs runs above a drip tray fitted with leak detection, and the condition of the coolant is measured continuously on the loop by an inline fluid quality valve, so that it is changed when its condition requires rather than on a calendar.

The practice engineering office
Fig. 02  Engineering officeNTS
Either hall

A conventional hall or an 800 VDC hall, from the same team.

We design conventional AC halls to hyperscaler reference requirements, and 800 VDC halls without UPS in which a rack can move from 5 kW to 600 kW without new panels, breakers or cables. Mixed halls run AC servers on in-rack DC-AC shelves. The choice is made in the feasibility model, on the client’s numbers, before design begins.

Our architects and MEP engineers are trained on NVIDIA and hyperscaler reference designs, and they carry a single drawing standard across every building they design.

CS-202.4Cooling analysisCFD Studio

Every hall is tested for heat before it is issued.

Before a mechanical package is issued, the hall layout is analysed in CFD Studio, our own computational fluid dynamics software. Hot islands are found and corrected on the drawing rather than on site, the cooling plant is checked against fifty years of weather for the site, and the results are issued with the design. The film shows the analysis from floor plan to report.

CFD Studio · analysis from plan to reportFull screen
Start a project

Send the brief. Receive the set.

Tell us the site, the load and the tenant. We will return the design scope, the programme and the team who will draw it.

ReplyWithin one working day, from an engineer
OfficesMumbai · Bangalore · Ahmedabad · Toronto
PracticeHyperNext Consulting Service, a proud member of HyperNext Group