Overview

Electricity is the largest operating cost a data centre will carry and the input it can least afford to lose. We secure the allocation and the connection first, then build a model of the facility’s demand hour by hour and use it to choose the combination of supply sources, contracts and storage that gives the lowest delivered cost for the reliability and renewable share the client requires.

In figures
Demand model8,760hEvery hour of the year, by phase
Supply sources7Tested against the demand profile
Method6stepsFrom demand profile to contract
Design ceiling1.30PUEDemand reduced before supply is bought
CS-103.1Allocation and connectivitySection A

The connection is the critical path.

A data centre can be designed in months and built in a year or two, but a new high-voltage connection can take longer than either if it is applied for late. We therefore prepare the load application at the feasibility stage, sized for the final campus rather than the first phase, and agree with the transmission and distribution companies the voltage level, the substation arrangement, the line route and the date on which power can be drawn.

Where the utility builds the substation, we coordinate its design with the campus master plan so that the incoming lines, the switchyard and the 33 kV distribution to each building are placed once and never moved.

A1

Load application

Contract demand by phase, load profile, power factor and harmonic statement, prepared from the feasibility model.

A2

Connection study

Voltage level, nearest substations, line route options, system strength and the utility’s own augmentation plans.

A3

Substation arrangement

Switchyard layout, transformer or solid-state conversion, metering and protection, coordinated with the master plan.

A4

Grid studies

Load flow, short circuit and protection studies in PowerStudio, submitted with the application where the utility requires them.

A5

Agreements

Connection, supply and, where applicable, open access agreements reviewed clause by clause with the client’s counsel.

A6

Energisation

Inspection, metering, testing and the sequence for first drawing power, planned with the construction programme.

CS-103.2The supply mixSection B

An optimised mix, chosen by the model.

No single source is cheapest at every hour. Utility supply is firm but carries cross-subsidy; solar is inexpensive by day and absent at night; wind follows its own seasons; exchange prices move by the quarter hour; storage costs money but moves energy to the hours where it is worth most. The right answer for a site depends on its demand, its state’s regulations and the client’s renewable commitment.

We build an hourly model of the facility’s demand across the year and test combinations of sources against it, including the open access charges, wheeling and banking terms and surcharges that apply in that state. The model returns the mix with the lowest delivered cost per unit for the reliability and renewable share the client has set, and shows how that answer changes as tariffs and regulations move.

RefSourceRole in the mixWhat we arrange
PS-01Utility supplyFirm base supply and back-up to every other sourceTariff category, contract demand, metering and supply agreement
PS-02Open accessBilateral purchase from generators through the gridEligibility, charges, scheduling and the approvals of the state nodal agency
PS-03Captive and group captiveLong-term renewable supply at a fixed cost from plants the consumer partly ownsStructure under the Electricity Rules, equity and consumption conditions, plant contracts
PS-04Power purchase agreementsLong-term contracts with third-party renewable generatorsTerm, price, curtailment, change in law and termination provisions
PS-05Power exchangesShort-term balancing, including green day-ahead and term-ahead productsExchange membership through a trader, bidding strategy and settlement
PS-06StorageMoving daytime renewable energy into evening and night hoursBattery sizing, siting, dispatch rules and metering
PS-07On-site generationEmergency supply only, sized to the critical loadGenerator rating, fuel storage, emission and noise compliance
CS-103.3MethodSection C

Six steps from demand to contract.

Power procurement is carried out alongside the feasibility study and the master plan, and its results feed both. The steps below are followed on every appointment.

PP-01

Demand profile

Hourly demand for each phase, built from the rack mix, the cooling plant and the annual efficiency profile drawn from site weather.

Output8,760-hour load model
PP-02

Regulatory map

Open access eligibility, charges, banking, wheeling and surcharges in the state, with the direction of pending regulation.

OutputState regulatory note
PP-03

Source options

Generators, plants and contracts available to the site, with their price, term and delivery profile.

OutputSource register
PP-04

Optimisation

The model tests combinations against the demand profile and returns the lowest delivered cost for the chosen reliability and renewable share.

OutputRecommended mix and sensitivity
PP-05

Contracting

Term sheets, negotiation and agreements with the utility, generators and traders, reviewed with the client’s counsel.

OutputExecuted agreements
PP-06

Operation

Scheduling, metering, settlement and an annual review of the mix as tariffs, regulation and the facility’s own load change.

OutputMonthly power report
CS-103.4Demand reductionSection D

The cheapest unit is the one never bought.

Procurement and design are treated as one problem. Every design we produce carries a PUE ceiling of 1.30, and the 800 VDC architecture converts power once from 33 kV to the rack rather than several times through transformers and UPS systems, which reduces both the energy lost as heat and the cooling needed to remove it. The power model is run on the design as drawn, so the savings appear in the contract demand and not only in a brochure.

Start a project

Secure the supply.

Send the site, the intended load and the date you need power. We will set out the connection route and the supply options the state allows.

ReplyWithin one working day, from an engineer
OfficesMumbai · Bangalore · Ahmedabad · Toronto
PracticeHyperNext Consulting Service, a proud member of HyperNext Group