Breaking Direct Current at the Rack
Solid-state protection and the panel that carries it
Why interruption without a current zero is a different problem. Selectivity when every device is fast. What removing the arc does to maintenance.
Abstract
Alternating current hands a protective device a free opportunity to interrupt, one hundred times a second. Direct current hands it nothing. This paper sets out how the HyperNext rack power panel protects an 800 volt network using solid-state breakers, what happens to selectivity when every device in the chain clears in microseconds, and why the change in arc-flash exposure matters more to the maintenance team than the change in clearing time matters to the equipment.
Contents
- 011. Where the panel sits
- 022. Interruption without a current zero
- 033. The breaker as a device
- 044. Selectivity when everything is fast
- 055. Arc flash, and what it does to maintenance
- 066. What else the panel carries
- 077. References and standards
Request the full paper
The complete paper, including all figures, tables, references, and citations, is available as PDF. Enter your details to receive it.
Request paper · HN-RP-012.pdfKey findings
- A solid-state breaker clears in about ten microseconds against roughly twenty milliseconds for a moulded case device, which is about three orders of magnitude less let-through energy at the same prospective fault.
- Selectivity cannot be arranged on time-current curves when every device is fast. Coordination is by current threshold and rate of rise instead, and it has to be proven by simulation before it is proven on site.
- Incident energy scales with arcing time. A fault never allowed to establish an arc changes the protective equipment a technician wears, which is a working-practice change rather than an equipment one.
- The panel carries one common frame with hot-swappable output cassettes, so a rack can be taken from 12 kW to 50 kW by changing a cassette rather than by rebuilding the electrical infrastructure behind it.
- Turning off current in microseconds does not remove the energy stored in the cable inductance. Clamping that energy is as much of the design as the switching is.