HN-RP-011 · · Engineering · 16 min read · 3,222 words · Version 1.0

Medium-Voltage Solid-State Transformation

33 kV to the rack without a distribution transformer

Topology and device physics. Why the magnetics shrink. How a direct current network clears a fault. What the efficiency claim actually counts.

Abstract

A conventional data centre converts its incoming supply up to six times before a processor can use it, and delivers roughly three quarters of what the meter records. HyperNext campuses take 33 kV to a medium-voltage solid-state transformer and run 800 volts direct current to the rack, delivering about 95 per cent. This paper sets out the topology, the device physics that makes it practical, the fault behaviour of a network with no current zero, and an honest account of what the conversion-stage comparison does and does not count.

Contents

  1. 011. The chain an 800 VDC campus does not build
  2. 022. What a solid-state transformer is, and what it is not
  3. 033. Device physics: why silicon carbide and not silicon
  4. 044. Clearing a fault without a current zero
  5. 055. The efficiency account, stage by stage
  6. 066. Copper, iron and floor area
  7. 077. References and standards

Request the full paper

The complete paper, including all figures, tables, references, and citations, is available as PDF. Enter your details to receive it.

Request paper · HN-RP-011.pdf

Key findings

  • The distribution transformer, the low-voltage switchgear lineup, the central uninterruptible supply and the battery plant are all absent from the chain. Ride-through moves to the rack.
  • The efficiency gain is paid twice over, because every watt lost in conversion becomes heat that a cooling plant then spends more power to remove.
  • Claiming two conversion stages against six is a system-level count. Three conversions happen inside the solid-state transformer itself, and the defensible comparison is measured end-to-end efficiency rather than a stage count.
  • Silicon carbide is what makes the architecture practical, not an incremental improvement on silicon: roughly a tenfold higher critical field allows a drift region about a tenth as thick at the same blocking voltage.
  • Direct current has no current zero, so interruption is a different engineering problem from alternating current. A solid-state breaker clears in microseconds where a mechanical device takes milliseconds.
  • There is no data centre standard for 800 VDC protection. The most mature published practice for medium-voltage DC is a shipboard document, IEEE 1709-2018.